Type A: Threaded bolt, embedded in mortar
A hole is drilled into 2 or 3 Internodes, as well as through the same number of diaphragms
from the end of the tube. A steel bolt is inserted through the holes in the nodes and then
mortar is injected through the holes in the culm wall to fix the steel pole.
|
Type B: Lateral steel tabs and bolts, embedded in mortar
2 to 3 internodes are drilled through completely at the end of a tube. Drilling has to be
carried out from outside everytime to not split the bamboo. Bolts with screw threads are
put through these holes and then the internodes are filled up with mortar. Now, a steel
sheet is connected with screws to the bolts. This steel sheet holds the second tube.
|
||